Operational Update At El Limon-Guajes Mine

 

TORONTO - Torex Gold Resources Inc. reported on the operations ramp-up of the ELG Mine in Mexico. Fred Stanford, President & CEO of Torex said, "The ramp up of the processing plant is tracking nicely ahead of plan, costs remain on budget, security and safety performance has been excellent, relationships with local communities continue to be productive, and the construction of production support facilities is drawing to a close. The next three milestones will be the declaration of commercial production, the resettlement of the El Limon village, and the commissioning of the El Limon Crusher / RopeCon. All of these milestones are on schedule for achievement in Q2 2016."

Processing Plant: The ramp-up remains on track for the declaration of commercial production in Q2/16; (60% of design throughput of 14,000 tonnes per day for 30 days); The first phase of the ramp-up was focused on achieving plant reliability / utilization. That phase is now completed, reliability / utilization at design levels have been demonstrated (90% utilization or 151 hours in a week); The design throughput rate per hour is approximately 650 tonnes per hour. The plant has consistently operated at 60% of that rate, approximately 400 tonnes per hour, through the 'reliability' ramp-up phase. During the past week additional grinding media has been added and the throughput rate is now approaching 500 tonnes per hour; To date a daily performance of 11,300 tonnes through the plant has been achieved. As additional grinding media is being added, the teams are honing their skills and procedures for the push to full production of 14,000 tonnes per day; The tailings filtration plant is delivering an excellent product for dry stack disposal; 13,500 ounces of gold have been produced, and 7,288 ounces of gold have been sold at an average price of $1,196 per ounce.

Mining at the Guajes pit re-started in January. El Limon pit pre-stripping has started and construction of the haul road to the El Limon Crusher is advancing ahead of schedule. The RopeCon is mechanically complete and preparations are underway for electrical commissioning. Full commissioning of the El Limon Crusher and the RopeCon is anticipated in the second quarter of 2016; Plant head grades have been above Life of Mine (LOM) grade. However, it is too early to make definitive statements about reconciliation to the geological model. We expect to start work on grade reconciliation after commercial production has been achieved and the plant metallurgy has stabilized.

Further geological work on the El Limon deposit has focused attention on an intrusive sill that projects from the main intrusive body. Much of the EL Limon deposit lies above this sill and conditions below the sill are also positive for gold skarn mineralization. This theory has support in drill results, in which 4 of 6 holes that pierced the sill, intersected mineralized skarn. There are also several highly magnetic targets underneath this sill, which have not been tested yet; These and other "near pit" exploration targets will be evaluated as opportunities to extend the ELG mine life.